Eden Prairie Community Center Aquatic Complex

- Client
- City of Eden Prairie
- Year
- 2012 to 2016
- ADC role
- Feasibility, aquatic design, construction-phase services
- Design team lead
- HGA Architects and Engineers
- Status
- Complete
A four-pool aquatic addition to the Twin Cities' best-known community center, designed with HGA, with no aquatics service calls since opening.
The Eden Prairie Community Center was already known across the Twin Cities for its three ice rinks and fitness amenities. As aquatic engineer to HGA Architects and Engineers, ADC designed its new aquatic complex in about 15,000 square feet of water: two 25 meter competition pools, one deep for springboard diving and one shallower for lessons and water exercise, a warm recreation pool with water slides, a climbing wall, zero-depth entry and play features, and a 20-person spa. The work ran from a 2012 feasibility study through 2014 bid documents to opening. Since then, HGA reports, not one call has come in about the aquatic systems.